PMP · Question #768
PMP Question #768: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #768. The question stem and answer options stay visible for context.
Question
A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments. What should the project manager do?
Options
- AChanged the duration of iterations to deliver more value
- BValidated the iteration goals with the customer
- CInvited the customer to the daily meetings
- DHelped the team redefine the MVP
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.