PMP · Question #596

PMP Question #596: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #596. The question stem and answer options stay visible for context.

Submitted by takeshi77· Apr 18, 2026People

Question

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing. What should the project manager have done to prevent this?

Options

  • AFacilitated cross-functional knowledge transfer during the project.
  • BAcquired more than one resource skilled in each component.
  • COutsourced development of the specific component to another team.
  • DRequested robust documentation for the component's build.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Team Development#Knowledge Transfer#Resource Management