PMP · Question #568

PMP Question #568: Real Exam Question with Answer & Explanation

The correct answer is B. Schedule one-to-one meetings and team-building meetings.. To address disengagement in a virtual team, a project manager should foster personal connections and team cohesion through one-to-one and team-building meetings.

Submitted by chiamaka_o· Apr 18, 2026People

Question

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged. How should the project manager approach this situation?

Options

  • AReduce the number of internal and external meetings.
  • BSchedule one-to-one meetings and team-building meetings.
  • CReview team assignments and reduce the workload.
  • DGive the team members a few days off to reduce stress_

Explanation

To address disengagement in a virtual team, a project manager should foster personal connections and team cohesion through one-to-one and team-building meetings.

Common mistakes.

  • A. While meeting fatigue can contribute to disengagement, reducing all meetings without understanding the root cause might hinder necessary communication and coordination.
  • C. Reviewing and reducing workload might be a solution if workload is the specific cause of disengagement, but it's not the first general approach before understanding the specific reasons for disengagement.
  • D. Giving team members days off is a reactive measure for stress reduction, but it does not address the underlying issues of disengagement or build long-term team cohesion.

Concept tested. Virtual team engagement and cohesion

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-resource-management

Topics

#Team Management#Team Engagement#Virtual Teams#Team Building