PMI
PMP · Question #568
PMP Question #568: Real Exam Question with Answer & Explanation
The correct answer is B. Schedule one-to-one meetings and team-building meetings.. To address disengagement in a virtual team, a project manager should foster personal connections and team cohesion through one-to-one and team-building meetings.
Submitted by chiamaka_o· Apr 18, 2026People
Question
An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged. How should the project manager approach this situation?
Options
- AReduce the number of internal and external meetings.
- BSchedule one-to-one meetings and team-building meetings.
- CReview team assignments and reduce the workload.
- DGive the team members a few days off to reduce stress_
Explanation
To address disengagement in a virtual team, a project manager should foster personal connections and team cohesion through one-to-one and team-building meetings.
Common mistakes.
- A. While meeting fatigue can contribute to disengagement, reducing all meetings without understanding the root cause might hinder necessary communication and coordination.
- C. Reviewing and reducing workload might be a solution if workload is the specific cause of disengagement, but it's not the first general approach before understanding the specific reasons for disengagement.
- D. Giving team members days off is a reactive measure for stress reduction, but it does not address the underlying issues of disengagement or build long-term team cohesion.
Concept tested. Virtual team engagement and cohesion
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-resource-management
Topics
#Team Management#Team Engagement#Virtual Teams#Team Building
Community Discussion
No community discussion yet for this question.