nerdexam
PMIPMI

PMP · Question #489

PMP Question #489: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #489. The question stem and answer options stay visible for context.

Submitted by yaw92· Apr 18, 2026People

Question

A project manager finished reviewing the project deliverables for the current iteration with the customer. A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated. What should the project manager do to address this issue?

Options

  • ACreate a change request and update the scope management plan
  • BConduct stakeholder identification and a project objectives review session
  • CUpdate the stakeholder list and fix the deliverables
  • DUpdate the project management plan and lessons learned

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder management#Stakeholder identification#Expectation management#Project objectives
Full PMP PracticeBrowse All PMP Questions