A project manager is leading a project with several stakeholders in other functional areas of the company. One of these stakeholders has just been promoted to lead another functional area, and remains

The correct answer is B. Stakeholder engagement plan. When a stakeholder's role and influence change due to a promotion, the project manager should ensure the project team updates the stakeholder engagement plan. This plan specifically details how to effectively involve and communicate with stakeholders, and changes in their role ne

Submitted by stefanr· Apr 18, 2026People

Question

A project manager is leading a project with several stakeholders in other functional areas of the company. One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project. What should the project manager have the project team update to ensure proper communications to stakeholders?

Options

  • AProject management plan
  • BStakeholder engagement plan
  • CStakeholder register
  • DCommunications management plan

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    76% (22)
  • C
    7% (2)
  • D
    3% (1)

Why each option

When a stakeholder's role and influence change due to a promotion, the project manager should ensure the project team updates the stakeholder engagement plan. This plan specifically details how to effectively involve and communicate with stakeholders, and changes in their role necessitate adjusting engagement strategies.

AProject management plan

The Project Management Plan is the overarching plan; while a change in a stakeholder might necessitate updates to components of it, the most direct and specific plan for communication *strategy* and engagement is the Stakeholder Engagement Plan.

BStakeholder engagement planCorrect

The stakeholder engagement plan outlines the strategies for effectively engaging stakeholders based on their influence, interest, and impact. A change in a stakeholder's role (like a promotion) directly impacts their influence and communication needs, so updating this plan ensures appropriate ongoing engagement.

CStakeholder register

The stakeholder register records basic information about stakeholders, and while it should be updated with the new role, it does not describe *how* to engage with them effectively or manage proper communications.

DCommunications management plan

The communications management plan defines *how*, *when*, *who*, and *what* information will be communicated; while it may need adjustments, the stakeholder engagement plan dictates the *strategy* for involving stakeholders and their communication needs, which then informs the communications management plan.

Concept tested: Stakeholder Engagement Plan Update

Source: https://www.pmi.org/learning/library/develop-stakeholder-engagement-plan-7049