PMP · Question #41

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team m

The correct answer is D. Invite all resources to the project manager's location to form a cohesive team until all deliverables. A project manager must ensure successful execution when a project requires team members from different continents.

Submitted by stefanr· Apr 18, 2026People

Question

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents. What should the project manager do to ensure a successful project execution?

Options

  • APlan for a meeting with the project sponsor to discuss the possibility of utilizing only local
  • BSend emails with information about the project deliverables on the first day of the project.
  • CConnect with every location and check their preferred methods of communication.
  • DInvite all resources to the project manager's location to form a cohesive team until all deliverables

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    13% (6)
  • C
    6% (3)
  • D
    77% (36)

Why each option

A project manager must ensure successful execution when a project requires team members from different continents.

APlan for a meeting with the project sponsor to discuss the possibility of utilizing only local

This option directly contradicts the company's stated requirement to include team members from different continents, indicating a failure to adhere to project constraints.

BSend emails with information about the project deliverables on the first day of the project.

While important, simply sending emails with project deliverables on the first day is insufficient for building the necessary team cohesion and understanding for a diverse, globally distributed team.

CConnect with every location and check their preferred methods of communication.

Connecting to check preferred communication methods is a good step but does not address the fundamental need for initial team building and establishing a shared project foundation across continents.

DInvite all resources to the project manager's location to form a cohesive team until all deliverablesCorrect

Bringing a globally distributed team together physically, especially at the start, helps build initial cohesion, trust, and a shared understanding of project goals and culture. This initial face-to-face interaction can overcome many communication barriers and cultural differences that often arise in virtual teams, laying a strong foundation for future collaboration.

Concept tested: Building global team cohesion

Topics

#Global Teams#Team Building#Team Cohesion#Communication Planning