A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of
The correct answer is A. Schedule a meeting with the new stakeholder.. To ensure a new interested stakeholder is fully aware of a strategic initiative's goals, objectives, benefits, and risks, the project manager should schedule a direct meeting with them.
Question
A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?
Options
- ASchedule a meeting with the new stakeholder.
- BShare the project status reports with the new stakeholder.
- CUpdate the stakeholder engagement plan.
- DAdd the new stakeholder to the communications management plan.
How the community answered
(67 responses)- A75% (50)
- B4% (3)
- C9% (6)
- D12% (8)
Why each option
To ensure a new interested stakeholder is fully aware of a strategic initiative's goals, objectives, benefits, and risks, the project manager should schedule a direct meeting with them.
Scheduling a direct meeting allows for a comprehensive, two-way communication session where the project manager can personally explain the project details (goals, objectives, benefits, risks) and address any immediate questions or concerns from the new stakeholder, ensuring full awareness and building rapport.
Simply sharing status reports provides ongoing updates but might not offer the comprehensive background information a new stakeholder needs to fully understand the project's foundational elements.
Updating the stakeholder engagement plan is a process step that follows initial engagement and assessment; the immediate action is to engage the stakeholder.
Adding the stakeholder to the communications management plan is an administrative step for ongoing communication, but it doesn't provide the initial, in-depth briefing required to ensure full awareness.
Concept tested: Initial engagement of a new project stakeholder
Source: https://www.pmi.org/learning/library/stakeholder-engagement-strategies-6842