PMP · Question #325
PMP Question #325: Real Exam Question with Answer & Explanation
The correct answer is D: Organize a team meeting to discuss the next course of action.. Upon observing potential missed deadlines due to resource delays, the project manager should first organize a team meeting to collaboratively understand the situation and determine the best course of action.
Question
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?
Options
- AReview the risk management plan to identify the response strategy.
- BEscalate the issue to the sponsor and debrief them about the situation.
- CReview the milestone list to determine which tasks can be fast-tracked.
- DOrganize a team meeting to discuss the next course of action.
Explanation
Upon observing potential missed deadlines due to resource delays, the project manager should first organize a team meeting to collaboratively understand the situation and determine the best course of action.
Common mistakes.
- A. While resource issues can be risks, reviewing the risk management plan might provide general strategies but won't give specific solutions for the current, active problem without team input.
- B. Escalation to the sponsor is premature without first understanding the full scope of the problem and potential internal solutions from the team.
- C. Fast-tracking is a potential solution, but deciding to fast-track without consulting the team about feasibility and other options is not the immediate next step.
Concept tested. Initial project manager response to project delays
Reference. https://www.pmi.org/learning/library/resolving-project-problems-using-team-6523
Topics
Community Discussion
No community discussion yet for this question.