PMP · Question #258
PMP Question #258: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #258. The question stem and answer options stay visible for context.
Submitted by kim_seoul· Apr 18, 2026People
Question
In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone. What should the project manager do?
Options
- AConsult the risk response plan.
- BUpdate the resource calendar.
- CIssue a request to the change control board (CCB).
- DAssign the tasks to another team member.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Resource Management#Team Management#Resource Calendar