PMP · Question #257
PMP Question #257: Real Exam Question with Answer & Explanation
The correct answer is B: Allow the team to decide on their own which option should be implemented.. After conducting spikes to gather information, the Scrum Master should empower the self-organizing team to make the final decision on the technical approach for feature delivery.
Question
A project manager is performing the role of scrum master for a team of developers. There is a conflict among the developers, generated by differences in how a feature can be delivered. The project manager organized a few spikes to resolve this conflict. What should the project manager do next?
Options
- AOrganize a multivoting event to achieve consensus of the whole team.
- BAllow the team to decide on their own which option should be implemented.
- COrganize more spike events until consensus of the team is reached.
- DAsk the project sponsor to decide which option should be implemented.
Explanation
After conducting spikes to gather information, the Scrum Master should empower the self-organizing team to make the final decision on the technical approach for feature delivery.
Common mistakes.
- A. While multivoting can be a tool for decision-making, it implies the Scrum Master is organizing the decision directly, rather than facilitating the team's self-organization to arrive at a decision.
- C. Organizing more spikes indefinitely without a clear path to decision-making is inefficient and can delay the project, as spikes are meant to gather just enough information to make an informed decision.
- D. Asking the project sponsor to decide undermines the development team's autonomy and expertise in technical matters, which goes against Agile principles of self-organizing teams.
Concept tested. Agile team self-organization & Scrum Master role
Reference. https://www.scrum.org/resources/scrum-guide
Topics
Community Discussion
No community discussion yet for this question.