An organization is adopting an agile mindset. On the first agile project, the project manager faced an issue because the team was unable to make decisions on time. What should the project manager do to address the problem?

Options

  • AAssess the situation to understand how the organization's culture impacts the decision-making
  • BAdopt an autocratic leadership style and dictate all decisions in order to speed up the team's
  • CInvite senior leadership to a team-building workshop and restate the importance of accountability
  • DDefine clear guidelines on how decisions should be made under the new organizational policy

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Transformation#Organizational Culture#Team Empowerment#Decision Making
Full PMP PracticeBrowse All PMP Questions