PMP · Question #1122
At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week. the project team realizes that the activities were executed in the wrong way b
The correct answer is D. Use a common communication terminology.. To prevent future misunderstandings and ensure correct execution of activities, the project manager should establish and use common communication terminology within the team.
Question
Options
- AConduct reviews prior to performing activities.
- BMonitor the team's performance metrics.
- CDocument the agreement in the meeting minutes.
- DUse a common communication terminology.
How the community answered
(55 responses)- A7% (4)
- B11% (6)
- C4% (2)
- D78% (43)
Why each option
To prevent future misunderstandings and ensure correct execution of activities, the project manager should establish and use common communication terminology within the team.
Conducting reviews prior to activities might catch misunderstandings but does not prevent them from occurring in the initial agreement phase.
Monitoring performance metrics tracks outcomes but does not address the underlying communication breakdown that caused the incorrect execution.
Documenting agreements in minutes is good practice but does not guarantee a common understanding if the terminology used within the documentation itself is ambiguous or interpreted differently by team members.
The root cause of the delay was different understandings among team members, so establishing common communication terminology ensures everyone interprets discussions and agreements uniformly, preventing future misinterpretations and ensuring consistent execution.
Concept tested: Effective communication strategies; Clarity in communication
Source: https://learn.microsoft.com/en-us/training/modules/manage-project-communications/4-improve-communication-skills