Question
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay. How should this situation be handled?
Options
- AHire a consulting company to address the robotic interface questions, when necessary, and to
- BAdd an experienced professional to the team to reinforce knowledge sharing and help grow team
- CCreate a separate team with experienced members who understand the technology and split the
- DUse a robotics vendor company to develop the interfaces so the team will not be held back by a