A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master's program will coincide with the
Sign in or unlock PMP to reveal the answer and full explanation for question #1091. The question stem and answer options stay visible for context.
Submitted by fernanda_arg· Apr 18, 2026People
Question
A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project. What should the project manager do?
Options
- ASuggest the team member postpone their enrollment in the master's program until the project is
- BAssess the team member's commitment to the master's program and its impact on project
- CAsk the team member to delegate some of their tasks to another colleague during the last phase
- DAsk the team member to inform human resources (HR) about their enrollment in the master's
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Team Management#Resource Management#Risk Assessment#Conflict Management