Question
A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software. What should the project manager do?
Options
- ADiscuss the testing requirements with a test engineer and negotiate the best approach to test the
- BMeet with a procurement specialist to negotiate with a company that specializes in software
- CMeet with the project team to collaboratively determine how the project manager can ensure the
- DRequest a meeting with the sponsor to change the scope to allow the development team to