Complete this sentence: _________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.

The correct answer is B. Report performance. Report performance is a project process that collects and distributes information on the project Answer option C is incorrect. Earned value management may be used as the tool and technique for determining project performance. Answer option D is incorrect. Monitor and control…

Stakeholder Communication

Question

Complete this sentence:

_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.

Options

  • ACorrective action
  • BReport performance
  • CEarned value management
  • DMonitor and control project performance

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    93% (42)
  • C
    2% (1)

Explanation

Report performance is a project process that collects and distributes information on the project Answer option C is incorrect. Earned value management may be used as the tool and technique for determining project performance. Answer option D is incorrect. Monitor and control project performance is not a project process so this choice is not valid. Answer option A is incorrect. Corrective action is a response to project performance to bring the project back into alignment with expectations.

Topics

#performance reporting#status reports#forecasts#progress measurement