PMI-SP · Question #216
Complete this sentence: _________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.
The correct answer is B. Report performance. Report performance is a project process that collects and distributes information on the project Answer option C is incorrect. Earned value management may be used as the tool and technique for determining project performance. Answer option D is incorrect. Monitor and control…
Question
Complete this sentence:
_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.
Options
- ACorrective action
- BReport performance
- CEarned value management
- DMonitor and control project performance
How the community answered
(45 responses)- A4% (2)
- B93% (42)
- C2% (1)
Explanation
Report performance is a project process that collects and distributes information on the project Answer option C is incorrect. Earned value management may be used as the tool and technique for determining project performance. Answer option D is incorrect. Monitor and control project performance is not a project process so this choice is not valid. Answer option A is incorrect. Corrective action is a response to project performance to bring the project back into alignment with expectations.