PMI-ACP · Question #82
PMI-ACP Question #82: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #82. The question stem and answer options stay visible for context.
Submitted by yuriko_h· Apr 18, 2026Adaptive Planning
Question
Which type of story would be used when an estimate is not available due to lack of knowledge of the technology required to implement the story?
Options
- ADefect
- BSlack
- CSpike
- DNonfunctional
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Spikes#Estimation#Uncertainty#Agile Story Types