PMI-ACP · Question #760
During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should…
The correct answer is B. Create a spike story to analyze the impact of the threshold requirement on current stories. A spike story is a time-boxed investigation used in agile to resolve uncertainty or explore unknowns - exactly what's needed when a new performance threshold requirement's impact on existing backlog stories is unclear. It produces knowledge (not shippable product) that enables…
Question
During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should the team do?
Options
- BCreate a spike story to analyze the impact of the threshold requirement on current stories
- CConduct design planning session to review the performance threshold requirement
- DIdentify the tasks for the new performance threshold requirement
How the community answered
(35 responses)- B77% (27)
- C14% (5)
- D9% (3)
Explanation
A spike story is a time-boxed investigation used in agile to resolve uncertainty or explore unknowns - exactly what's needed when a new performance threshold requirement's impact on existing backlog stories is unclear. It produces knowledge (not shippable product) that enables the team to make informed decisions. Option C (design planning) is premature without first understanding the impact. Option D (identifying tasks) assumes the work is understood, which it isn't yet. Creating a spike is the proper agile technique to reduce uncertainty before committing to implementation.
Topics