nerdexam
PMI

PMI-ACP · Question #632

The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?

The correct answer is D. Use the team's historical velocity to calculate a range of features that can be delivered. Long-range estimates in agile are best expressed as a range based on empirical data - specifically the team's historical velocity. By calculating velocity over past iterations and projecting it forward, the scrum master can provide a realistic, defensible range of features…

Submitted by krish.m· Apr 18, 2026Adaptive Planning

Question

The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?

Options

  • ACommit to a specific feature set for delivery
  • BExplain that a commitment will be provided after planning
  • CHave the team estimate in story points to commit to a specific set of features
  • DUse the team's historical velocity to calculate a range of features that can be delivered

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    15% (3)
  • D
    75% (15)

Explanation

Long-range estimates in agile are best expressed as a range based on empirical data - specifically the team's historical velocity. By calculating velocity over past iterations and projecting it forward, the scrum master can provide a realistic, defensible range of features rather than a false-precision commitment. Option A (commit to specific features) creates a fixed-scope promise that ignores agile's embrace of change and uncertainty. Option B (wait until after planning) is unhelpful when a high-level forecast is legitimately needed by stakeholders. Option C (estimate in story points to commit to a specific set) is too rigid - velocity-based ranges account for variability and are more honest about uncertainty.

Topics

#Agile Forecasting#Historical Velocity#Scrum Master#Long-term Planning

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice