The correct answer is A: Manages daily tasks of the team members. Managing team members' daily tasks (A) is a characteristic of traditional, command-and-control project management — not agile. An Agile project manager (or Agile leader) coaches, facilitates, and removes impediments while trusting the self-organizing team to determine how to ac

Submitted by stefanr· Apr 18, 2026Team Performance

Question

Which of the following is NOT a characteristic of Agile project manager?

Options

  • AManages daily tasks of the team members
  • BAssumes different leadership styles for different stages of team formation
  • CAllows team to self-manage
  • DFacilitates collaboration

Explanation

Managing team members' daily tasks (A) is a characteristic of traditional, command-and-control project management — not agile. An Agile project manager (or Agile leader) coaches, facilitates, and removes impediments while trusting the self-organizing team to determine how to accomplish their work. The agile PM assumes different leadership styles as the team matures (B — situational leadership), allows self-management (C), and facilitates collaboration (D). Micromanaging daily tasks undermines team autonomy and ownership, which are core agile values.

Topics

#Agile Leadership#Servant Leadership#Self-Organizing Teams#Team Empowerment

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions