PMI-ACP · Question #628
A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate. What should the agile project leader do?
The correct answer is B. Assure the new member that inputs on impediments are valued, and demonstrate this at the next. The main issue here is reluctance to communicate. The agile project leader also assumes the role of the servant leader. Additionally, a facilitator encourages collaboration through interactive meetings, informal dialog, and knowledge sharing. Servant leaders do this by becoming…
Question
A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate. What should the agile project leader do?
Options
- ABring up the new member's impediments at the next meeting to demonstrate team support of
- BAssure the new member that inputs on impediments are valued, and demonstrate this at the next
- CHave a senior lead work with the new member to avoid a negative impact on team productivity
- DPrivately work with the new member to address any impediments
How the community answered
(39 responses)- A3% (1)
- B82% (32)
- C5% (2)
- D10% (4)
Explanation
The main issue here is reluctance to communicate. The agile project leader also assumes the role of the servant leader. Additionally, a facilitator encourages collaboration through interactive meetings, informal dialog, and knowledge sharing. Servant leaders do this by becoming impartial bridge-builders and coaches, rather than by making decisions for which others should be responsible. Agile creates a culture of transparency: people show and share their work throughout development. This sharing of interim deliverables and being open and honest about successes, failures, and current state is transparency. Transparency requires courage.
Topics
Community Discussion
No community discussion yet for this question.