PMI-ACP · Question #625

PMI-ACP Question #625: Real Exam Question with Answer & Explanation

The correct answer is C: Refer to the remaining prioritized backlog items. The product backlog is the single authoritative, prioritized source of work. When an iteration's capacity still has room, the team pulls the next highest-priority items from the backlog to fill remaining capacity — this ensures the team is always working on the most valuable it

Submitted by yasin.bd· Apr 18, 2026Adaptive Planning

Question

During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration's remaining scope?

Options

  • AConvince the team to stop planning and keep the size small
  • BIdentify the technically minimal and achievable tasks
  • CRefer to the remaining prioritized backlog items
  • DSelect some of the smallest items from the backlog

Explanation

The product backlog is the single authoritative, prioritized source of work. When an iteration's capacity still has room, the team pulls the next highest-priority items from the backlog to fill remaining capacity — this ensures the team is always working on the most valuable items. Option A (stop planning and keep size small) wastes available capacity and contradicts the goal of maximizing value delivery. Option B (technically minimal tasks) ignores business priority in favor of technical convenience. Option D (smallest items) selects by size rather than business value, which is contrary to agile prioritization principles.

Topics

#Iteration Planning#Product Backlog#Scope Definition#Prioritization