PMI-ACP · Question #613
A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity. What should the team…
The correct answer is D. Break non-functional requirements into those that can be delivered in the given sprint. Agile teams handle oversized work items by breaking them down into smaller, deliverable increments. This preserves the sprint timebox, maintains a sustainable pace, and still delivers partial value. Ignoring non-functional requirements (A) risks quality and technical debt…
Question
A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity. What should the team do?
Options
- AEstimate only functional requirements that will impact product quality
- BAdd team resources
- CRefer the issue to the product owner
- DBreak non-functional requirements into those that can be delivered in the given sprint
How the community answered
(34 responses)- A3% (1)
- B6% (2)
- C9% (3)
- D82% (28)
Explanation
Agile teams handle oversized work items by breaking them down into smaller, deliverable increments. This preserves the sprint timebox, maintains a sustainable pace, and still delivers partial value. Ignoring non-functional requirements (A) risks quality and technical debt. Adding resources mid-sprint (B) disrupts the team and rarely improves output immediately. Referring to the product owner (C) may be needed for prioritization, but the team first has an obligation to attempt to fit the work by decomposing it.