nerdexam
PMIPMI

PMI-ACP · Question #609

PMI-ACP Question #609: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #609. The question stem and answer options stay visible for context.

Submitted by joshua94· Apr 18, 2026Value-driven Delivery

Question

After completing the release plan, the team realizes that the project is very likely to have a negative ROI. What should the team do?

Options

  • APrioritize the backlog, and remove low-priority stories from the release plan to ensure a positive
  • BReplace some team members to reduce the release costs and minimize a negative ROI
  • CPerform a root-cause analysis to remove waste from the delivery process and increase the ROI
  • DCommunicate the risk of a negative ROI to the stakeholders, and update the release plan

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#ROI#Risk management#Stakeholder communication#Adaptive planning
Full PMI-ACP PracticeBrowse All PMI-ACP Questions