PMI-ACP · Question #602

PMI-ACP Question #602: Real Exam Question with Answer & Explanation

The correct answer is C: It trended behind schedule and did not complete everything on time. On a burndown chart, the ideal trend line shows remaining work decreasing steadily to zero by the end of the iteration. When the actual remaining work line stays above the ideal line — meaning less work is being completed than planned — the team is trending behind schedule. I

Submitted by klara.se· Apr 18, 2026Adaptive Planning

Question

Based on the burndown chart, what is the iteration's status?

Options

  • AIt trended ahead of schedule and completed everything on time
  • BIt look more time than expected and had to be lengthened
  • CIt trended behind schedule and did not complete everything on time
  • DIt took less time than expected and had to be shortened

Explanation

On a burndown chart, the ideal trend line shows remaining work decreasing steadily to zero by the end of the iteration. When the actual remaining work line stays above the ideal line — meaning less work is being completed than planned — the team is trending behind schedule. If the actual line never reaches zero by the sprint end date, the team did not complete all planned work. Answer C describes this pattern: the team trended behind schedule and failed to complete everything on time. The other choices describe scenarios where the actual line is at or below the ideal line, which would indicate being on track or ahead of schedule.

Topics

#Burndown chart#Iteration status#Agile metrics#Progress tracking

Community Discussion

No community discussion yet for this question.