PMI-ACP · Question #579
During a sprint review, the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint. What should the product owner do next?
The correct answer is B. Create a user story for this new improvement and prioritize it for the next sprint. When the product owner identifies a required improvement during a sprint review, the appropriate action is to create a user story and prioritize it for the next sprint immediately. Because the product owner has flagged it as a required improvement-not a nice-to-have-it warrants…
Question
During a sprint review, the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint. What should the product owner do next?
Options
- ACreate a user story for this new improvement and put it in the product backlog for prioritization
- BCreate a user story for this new improvement and prioritize it for the next sprint
- CDocument it as a requirement creep
- DAsk the team to take on additional story points to improve the UI
How the community answered
(60 responses)- A3% (2)
- B78% (47)
- C12% (7)
- D7% (4)
Explanation
When the product owner identifies a required improvement during a sprint review, the appropriate action is to create a user story and prioritize it for the next sprint immediately. Because the product owner has flagged it as a required improvement-not a nice-to-have-it warrants explicit prioritization for the upcoming sprint rather than being left in the general backlog for later consideration (A). Labeling it requirement creep (C) dismisses a valid need, and asking the team to absorb additional points mid-sprint (D) disrupts the current sprint commitment.
Topics
Community Discussion