nerdexam
PMI

PMI-ACP · Question #570

A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration. Since items A and B are similar,

The correct answer is A. Defer starting the design of item B until the second iteration is being planned. Agile and Lean principles discourage starting work outside the current iteration's scope, as this creates partially done work - a form of waste - and can distract the team from completing item A. The team's priority must be completing their current sprint commitment. Additionally

Submitted by omar99· Apr 18, 2026Adaptive Planning

Question

A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration. Since items A and B are similar, a team member suggests beginning the design of item B. What should the agile practitioner do?

Options

  • ADefer starting the design of item B until the second iteration is being planned
  • BProceed with the design of item B, since it will hasten the second iteration
  • CEscalate the issue to the customer, and obtain their approval before starting the design of item B
  • DLog the issue in the risk register, and request change control board (CCB) approval

How the community answered

(41 responses)
  • A
    80% (33)
  • B
    2% (1)
  • C
    5% (2)
  • D
    12% (5)

Explanation

Agile and Lean principles discourage starting work outside the current iteration's scope, as this creates partially done work - a form of waste - and can distract the team from completing item A. The team's priority must be completing their current sprint commitment. Additionally, requirements for item B may change before its iteration is planned. Starting early based on assumed similarity risks rework. Escalating to the customer (C) or involving a CCB (D) introduces heavyweight governance inappropriate for this scenario.

Topics

#Adaptive Planning#Iteration Management#Work In Progress (WIP)#Focus

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice