PMI-ACP · Question #550
PMI-ACP Question #550: Real Exam Question with Answer & Explanation
The correct answer is D: Complex/Unknown/Risky/Big. In Agile, an Epic is a large user story that is too big to deliver in a single iteration. The CURB acronym characterizes what makes a story an epic: Complex (has many unknowns or dependencies), Unknown (requirements are not yet well understood), Risky (carries significant technic
Question
The definition of an Epic can be written using the acronym CURB. What does CURB stand for:
Options
- ACreate/Update/Replace/Big
- BCompound/Unknown/Risky/Basic
- CComplicated/Unusual/Really/Big
- DComplex/Unknown/Risky/Big
Explanation
In Agile, an Epic is a large user story that is too big to deliver in a single iteration. The CURB acronym characterizes what makes a story an epic: Complex (has many unknowns or dependencies), Unknown (requirements are not yet well understood), Risky (carries significant technical or business risk), or Big (too large to complete within one sprint). When a story meets one or more CURB criteria, it should be decomposed into smaller, manageable user stories before development.
Topics
Community Discussion
No community discussion yet for this question.