PMI-ACP · Question #541
Which of the following is NOT a prioritization technique?
The correct answer is E. Planning Poker. Planning Poker (E) is an estimation technique, not a prioritization technique. It is used to reach consensus on the effort or complexity of work items (typically using story points), not to determine the order or priority of features. User Story Mapping, Kano Analysis, and…
Question
Which of the following is NOT a prioritization technique?
Options
- AUser Story Mapping
- BKano analysis
- CMinimally Marketable Features (MMF)
- DKitchen Prioritization
- EPlanning Poker
How the community answered
(28 responses)- A4% (1)
- D7% (2)
- E89% (25)
Explanation
Planning Poker (E) is an estimation technique, not a prioritization technique. It is used to reach consensus on the effort or complexity of work items (typically using story points), not to determine the order or priority of features. User Story Mapping, Kano Analysis, and Minimally Marketable Features (MMF) are all legitimate prioritization techniques used to determine what to build next and in what order.