The correct answer is A: To collaborate with stakeholders. The Sprint Review is a collaborative working session — not a status meeting — held at the end of each Sprint. Its purposes include: (A) collaborating with stakeholders to gather feedback, (B) inspecting the Increment and adapting the Product Backlog based on what was learned,
Question
What is the purpose of the Sprint Review? (Choose three.)
Options
- ATo collaborate with stakeholders
- BTo inspect and adapt
- CTo provide status on the Sprint
- DTo demonstrate what is "Done"
Explanation
The Sprint Review is a collaborative working session — not a status meeting — held at the end of each Sprint. Its purposes include: (A) collaborating with stakeholders to gather feedback, (B) inspecting the Increment and adapting the Product Backlog based on what was learned, and (D) demonstrating the 'Done' Increment to stakeholders. Option C ('provide status on the Sprint') is incorrect because Sprint Reviews are not status reports; they are focused on the product Increment and future direction.
Topics
Community Discussion
No community discussion yet for this question.