PMI-ACP · Question #501
PMI-ACP Question #501: Real Exam Question with Answer & Explanation
The correct answer is A: The Product Owner can clarify the backlog during the Sprint. A is true: The Product Owner is available during the Sprint to answer questions and clarify backlog items for the Development Team. C is true: Ordering (prioritizing) the Product Backlog is a core accountability of the Product Owner. B is false: The Development Team estimates the
Question
Select the statements that are TRUE about the Product Owner. (Choose two.)
Options
- AThe Product Owner can clarify the backlog during the Sprint
- BThe Product Owner estimates the size of the Sprint backlog
- CThe Product Owner prioritizes the Product backlog
- DThe Product Owner defines the Sprint Goal before the Sprint Planning meeting
Explanation
A is true: The Product Owner is available during the Sprint to answer questions and clarify backlog items for the Development Team. C is true: Ordering (prioritizing) the Product Backlog is a core accountability of the Product Owner. B is false: The Development Team estimates the size of backlog items, not the Product Owner. D is false: The Sprint Goal is created collaboratively during Sprint Planning, not defined unilaterally by the Product Owner beforehand.
Topics
Community Discussion
No community discussion yet for this question.