PMI-ACP · Question #501

PMI-ACP Question #501: Real Exam Question with Answer & Explanation

The correct answer is A: The Product Owner can clarify the backlog during the Sprint. A is true: The Product Owner is available during the Sprint to answer questions and clarify backlog items for the Development Team. C is true: Ordering (prioritizing) the Product Backlog is a core accountability of the Product Owner. B is false: The Development Team estimates the

Submitted by cyberguy42· Apr 18, 2026Value-driven Delivery

Question

Select the statements that are TRUE about the Product Owner. (Choose two.)

Options

  • AThe Product Owner can clarify the backlog during the Sprint
  • BThe Product Owner estimates the size of the Sprint backlog
  • CThe Product Owner prioritizes the Product backlog
  • DThe Product Owner defines the Sprint Goal before the Sprint Planning meeting

Explanation

A is true: The Product Owner is available during the Sprint to answer questions and clarify backlog items for the Development Team. C is true: Ordering (prioritizing) the Product Backlog is a core accountability of the Product Owner. B is false: The Development Team estimates the size of backlog items, not the Product Owner. D is false: The Sprint Goal is created collaboratively during Sprint Planning, not defined unilaterally by the Product Owner beforehand.

Topics

#Product Owner Role#Scrum Roles#Backlog Management#Value Maximization

Community Discussion

No community discussion yet for this question.