PMI-ACP · Question #5
PMI-ACP Question #5: Real Exam Question with Answer & Explanation
The correct answer is B: Customer value. In Agile, the Product Backlog is ordered primarily by customer value — stories that deliver the most value to the customer are developed first. This maximizes ROI early in the project and ensures that if the project is cut short, the highest-value features are already delivered
Question
Which of the following drivers is the most important factor in determining the order in which stories will be developed?
Options
- ARelative cost
- BCustomer value
- CDevelopment effort
- DDependencies
Explanation
In Agile, the Product Backlog is ordered primarily by customer value — stories that deliver the most value to the customer are developed first. This maximizes ROI early in the project and ensures that if the project is cut short, the highest-value features are already delivered. While relative cost, development effort, and dependencies are all considered, they are secondary factors used to refine or adjust the priority order. Customer value (answer B) is the foundational driver behind backlog prioritization in frameworks like Scrum and XP.
Topics
Community Discussion
No community discussion yet for this question.