PMI
PMI-ACP · Question #47
The following chart lists stories for a release of an Agile project: If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #47. The question stem and answer options stay visible for context.
Submitted by yaw92· Apr 18, 2026Adaptive Planning
Question
The following chart lists stories for a release of an Agile project:
If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
Options
- A3
- B4
- C5
- D7
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Velocity#Release Planning#Story Points#Iterations