PMI-ACP Question #466: Real Exam Question with Answer & Explanation

The correct answer is C: The Product Owner. Only the Product Owner has the authority to cancel a Sprint, per the Scrum Guide. This reflects the PO's accountability for the value of the product and the Sprint Goal. While stakeholders, the Scrum Master, or the Development Team may influence the decision, the formal authority

Submitted by eva_at· Apr 18, 2026Value-driven Delivery

Question

Who can cancel a Sprint?

Options

  • AThe Development Team
  • BExecutive Stakeholders
  • CThe Product Owner
  • DThe Scrum Master

Explanation

Only the Product Owner has the authority to cancel a Sprint, per the Scrum Guide. This reflects the PO's accountability for the value of the product and the Sprint Goal. While stakeholders, the Scrum Master, or the Development Team may influence the decision, the formal authority rests solely with the Product Owner.

Topics

#Sprint cancellation#Product Owner responsibilities#Scrum roles#Agile governance