PMI-ACP · Question #440

PMI-ACP Question #440: Real Exam Question with Answer & Explanation

The correct answer is D: The definition of "Done" is one that would allow the development work to be ready for a release.. In Scrum, the Definition of Done (DoD) is a shared, formal description of the state of the Increment when it meets the quality standards required for the product. The key criterion is that the Increment must be potentially releasable — not just passing QA or having documentatio

Submitted by fatema_kw· Apr 18, 2026Value-driven Delivery

Question

What is the best definition of "Done"?

Options

  • AWhatever will please the Product Owner
  • BIt is determined by the Scrum Master
  • CThe prodct has passed QA and has all of the required release documentation
  • DThe definition of "Done" is one that would allow the development work to be ready for a release.

Explanation

In Scrum, the Definition of Done (DoD) is a shared, formal description of the state of the Increment when it meets the quality standards required for the product. The key criterion is that the Increment must be potentially releasable — not just passing QA or having documentation (too narrow), not defined by the Scrum Master alone, and not simply whatever pleases the Product Owner. Option D captures the essential purpose: work is Done when it could be released.

Topics

#Definition of Done#Agile Quality#Scrum Framework#Potentially Releasable Increment