PMI-ACP · Question #432
PMI-ACP Question #432: Real Exam Question with Answer & Explanation
The correct answer is B: Cumulative story point Burndown chart. A Cumulative story point Burndown chart (also called a release burndown) tracks the total story points remaining across multiple iterations at the release level, allowing teams to see cumulative progress — i.e., how many total points have been completed by the end of each itera
Question
Which chart shows the total number of story points completed through the end of each iteration?
Options
- AIteration Burndown chart
- BCumulative story point Burndown chart
- CDaily Burndown chart
- DBurnup chart
Explanation
A Cumulative story point Burndown chart (also called a release burndown) tracks the total story points remaining across multiple iterations at the release level, allowing teams to see cumulative progress — i.e., how many total points have been completed by the end of each iteration. This is distinct from an Iteration Burndown (which tracks remaining work within a single iteration day by day) and a Daily Burndown (within-iteration, daily granularity). While a Burnup chart also shows cumulative completion, in the context of this question the cumulative release-level burndown is the identified answer.
Topics
Community Discussion
No community discussion yet for this question.