PMI-ACP · Question #414

Wideband Delphi is used by an Agile Project manager to support what activity?

The correct answer is C. Estimation. Wideband Delphi is a consensus-based estimation technique. A group of experts independently estimate effort or duration for tasks, then anonymously share their estimates. Differences are discussed openly, and the process repeats until the group converges on a consensus. It is…

Submitted by lukas.cz· Apr 18, 2026Adaptive Planning

Question

Wideband Delphi is used by an Agile Project manager to support what activity?

Options

  • APrioritization
  • BScheduling
  • CEstimation
  • DRisk Management

How the community answered

(64 responses)
  • A
    2% (1)
  • B
    3% (2)
  • C
    94% (60)
  • D
    2% (1)

Explanation

Wideband Delphi is a consensus-based estimation technique. A group of experts independently estimate effort or duration for tasks, then anonymously share their estimates. Differences are discussed openly, and the process repeats until the group converges on a consensus. It is specifically designed for estimation, not prioritization, scheduling, or risk management.

Topics

#Wideband Delphi#Estimation#Agile Estimation#Planning