PMI-ACP · Question #414
Wideband Delphi is used by an Agile Project manager to support what activity?
The correct answer is C. Estimation. Wideband Delphi is a consensus-based estimation technique. A group of experts independently estimate effort or duration for tasks, then anonymously share their estimates. Differences are discussed openly, and the process repeats until the group converges on a consensus. It is…
Question
Wideband Delphi is used by an Agile Project manager to support what activity?
Options
- APrioritization
- BScheduling
- CEstimation
- DRisk Management
How the community answered
(64 responses)- A2% (1)
- B3% (2)
- C94% (60)
- D2% (1)
Explanation
Wideband Delphi is a consensus-based estimation technique. A group of experts independently estimate effort or duration for tasks, then anonymously share their estimates. Differences are discussed openly, and the process repeats until the group converges on a consensus. It is specifically designed for estimation, not prioritization, scheduling, or risk management.