nerdexam
PMI

PMI-ACP · Question #409

What is the Agile term for the time period when some or all of the following occur: beta testing, regression testing, product integration, integration testing, documentation, defect fixing?

The correct answer is C. Tail. In Agile, the 'Tail' (also called the 'Release Tail' or 'Hardening Sprint' in some frameworks) refers to the period at the end of a project or release cycle dedicated to stabilization activities - beta testing, regression testing, integration, documentation, and defect fixing…

Submitted by haruto_sh· Apr 18, 2026Value-driven Delivery

Question

What is the Agile term for the time period when some or all of the following occur: beta testing, regression testing, product integration, integration testing, documentation, defect fixing?

Options

  • ASpike
  • BCode Freeze
  • CTail
  • DLag

How the community answered

(31 responses)
  • B
    3% (1)
  • C
    94% (29)
  • D
    3% (1)

Explanation

In Agile, the 'Tail' (also called the 'Release Tail' or 'Hardening Sprint' in some frameworks) refers to the period at the end of a project or release cycle dedicated to stabilization activities - beta testing, regression testing, integration, documentation, and defect fixing. It represents the work needed to finalize and ship the product after the main development iterations are complete. A 'Spike' is a time-boxed research task; 'Code Freeze' is a point in time rather than a period; 'Lag' is a scheduling term unrelated to this concept.

Topics

#Agile Terminology#Release Preparation#Testing Phases#Defect Management

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice