PMI-ACP · Question #395

Which Agile estimation technique is based upon relative sizing?

The correct answer is C. Story points. Story points estimate effort using relative sizing-comparing stories to each other rather than assigning absolute time values. A story worth 8 points is roughly twice as complex or effortful as one worth 4 points, but no specific hours are implied. Ideal time (option A) is an…

Submitted by priya_blr· Apr 18, 2026Adaptive Planning

Question

Which Agile estimation technique is based upon relative sizing?

Options

  • AIdeal time
  • BBottom up
  • CStory points
  • DLittle's Law

How the community answered

(21 responses)
  • A
    5% (1)
  • C
    95% (20)

Explanation

Story points estimate effort using relative sizing-comparing stories to each other rather than assigning absolute time values. A story worth 8 points is roughly twice as complex or effortful as one worth 4 points, but no specific hours are implied. Ideal time (option A) is an absolute measure (e.g., 'how long if there were no interruptions'). Bottom-up (option B) is a cost-estimation approach that sums detailed task estimates. Little's Law (option D) is a queuing-theory formula relating throughput, cycle time, and work-in-progress-not an estimation technique.

Topics

#Agile estimation#Story points#Relative sizing#Adaptive planning

Community Discussion

No community discussion yet for this question.