nerdexam
PMI

PMI-ACP · Question #373

What type of time estimation excludes non-programming time?

The correct answer is A. Ideal Time. Ideal Time (also called Ideal Days or Ideal Hours) is an estimation unit that represents how long a task would take if the developer worked on it uninterrupted - no meetings, no emails, no context-switching, no administrative work. It intentionally strips away all…

Submitted by akirajp· Apr 18, 2026Adaptive Planning

Question

What type of time estimation excludes non-programming time?

Options

  • AIdeal Time
  • BCalendar time
  • CDuration
  • DReal Time

How the community answered

(29 responses)
  • A
    86% (25)
  • B
    3% (1)
  • C
    7% (2)
  • D
    3% (1)

Explanation

Ideal Time (also called Ideal Days or Ideal Hours) is an estimation unit that represents how long a task would take if the developer worked on it uninterrupted - no meetings, no emails, no context-switching, no administrative work. It intentionally strips away all non-programming activities. Calendar Time, by contrast, reflects real-world elapsed time and includes all interruptions and overhead. Teams apply a velocity factor to convert Ideal Time estimates into actual Calendar Time commitments.

Topics

#Ideal time#Agile estimation#Time estimation#Velocity

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice