PMI-ACP · Question #362
PMI-ACP Question #362: Real Exam Question with Answer & Explanation
The correct answer is B: The project is behind schedule. A burndown chart tracks remaining work (y-axis) over time (x-axis). The 'expected' or 'ideal' line shows the planned rate of work completion. If the actual remaining work line is ABOVE the ideal line, it means more work remains than planned at that point in the sprint or project
Question
In a burndown chart, if the remaining work line is above the expected work line, what does this signify?
Options
- AThe project is ahead of schedule
- BThe project is behind schedule
- CThe resources are performing above expectation
- DThe project is being well managed
Explanation
A burndown chart tracks remaining work (y-axis) over time (x-axis). The 'expected' or 'ideal' line shows the planned rate of work completion. If the actual remaining work line is ABOVE the ideal line, it means more work remains than planned at that point in the sprint or project — the team is burning down work slower than expected, indicating the project is behind schedule.