PMI-ACP · Question #328
Who is responsible for change management in Scrum projects?
The correct answer is D. Product Owner. In Scrum, the Product Owner is responsible for change management. They own the product backlog and have the authority to accept, reject, or reprioritize change requests based on business value, stakeholder input, and project goals. There is no traditional Project Manager role…
Question
Who is responsible for change management in Scrum projects?
Options
- AProject Manager
- BProject Sponsor
- CScrum Master
- DProduct Owner
How the community answered
(56 responses)- A4% (2)
- B7% (4)
- C2% (1)
- D88% (49)
Explanation
In Scrum, the Product Owner is responsible for change management. They own the product backlog and have the authority to accept, reject, or reprioritize change requests based on business value, stakeholder input, and project goals. There is no traditional Project Manager role in Scrum. The Scrum Master removes impediments and coaches the team but does not control scope or priority. The Product Sponsor provides funding and strategic direction but is not responsible for day-to-day change decisions.
Topics
Community Discussion
No community discussion yet for this question.