All of the following are metrics used in Agile except:
The correct answer is A. Real Time. 'Real Time' is not a recognized Agile metric. Standard Agile metrics include: Velocity (the amount of work completed per iteration), Cycle Time (the time from when work starts to when it is delivered), Lead Time, Escaped Defects (defects found by customers after release), and…
Question
All of the following are metrics used in Agile except:
Options
- AReal Time
- BVelocity
- CEscaped defects
- DCycle time
How the community answered
(44 responses)- A95% (42)
- B2% (1)
- D2% (1)
Explanation
'Real Time' is not a recognized Agile metric. Standard Agile metrics include: Velocity (the amount of work completed per iteration), Cycle Time (the time from when work starts to when it is delivered), Lead Time, Escaped Defects (defects found by customers after release), and Burndown/Burnup Charts. These metrics provide actionable data about team performance and product quality. 'Real Time' is vague and not a defined Agile measurement concept.
Topics
Community Discussion
No community discussion yet for this question.