PMI-ACP · Question #299

Traditional Project Management uses the Work Breakdown Structure to develop requirements in terms of activities. What type of breakdown structure is used in Agile for this purpose?

The correct answer is A. Feature Breakdown Structure. In traditional project management, the Work Breakdown Structure (WBS) decomposes scope into deliverables and activities. In Agile, the equivalent decomposition is a Feature Breakdown Structure (FBS), which breaks down a product into themes, features, and user stories. The FBS…

Submitted by takeshi77· Apr 18, 2026Adaptive Planning

Question

Traditional Project Management uses the Work Breakdown Structure to develop requirements in terms of activities. What type of breakdown structure is used in Agile for this purpose?

Options

  • AFeature Breakdown Structure
  • BProduct Roadmap
  • CProduct Breakdown Structure
  • DSprint Backlog

How the community answered

(42 responses)
  • A
    93% (39)
  • C
    5% (2)
  • D
    2% (1)

Explanation

In traditional project management, the Work Breakdown Structure (WBS) decomposes scope into deliverables and activities. In Agile, the equivalent decomposition is a Feature Breakdown Structure (FBS), which breaks down a product into themes, features, and user stories. The FBS is hierarchical and supports iterative delivery. A Product Roadmap (B) is a high-level timeline, not a decomposition structure. A Product Breakdown Structure (C) is more of a traditional concept. A Sprint Backlog (D) is a sprint-level artifact, not a product-level decomposition.

Topics

#Feature Breakdown Structure#Agile requirements#Product decomposition#Adaptive planning