At the end of first iteration, the team finishes User Stories A, Band 50% of C. What is the team velocity?
The correct answer is B. 9. In Agile, velocity only counts User Stories that are fully 'Done' according to the Definition of Done. Partially completed work (50% of Story C) does not count toward velocity because it has not met the exit criteria and delivers no confirmed value. Therefore, only Stories A…
Question
At the end of first iteration, the team finishes User Stories A, Band 50% of C. What is the team velocity?
Options
- A11.5
- B9
- C14
- D16
How the community answered
(55 responses)- A9% (5)
- B84% (46)
- C2% (1)
- D5% (3)
Explanation
In Agile, velocity only counts User Stories that are fully 'Done' according to the Definition of Done. Partially completed work (50% of Story C) does not count toward velocity because it has not met the exit criteria and delivers no confirmed value. Therefore, only Stories A and B are counted, which together total 9 story points. The 11.5 option would result from incorrectly counting half of Story C's points (e.g., if C = 5 points, then 9 + 2.5 = 11.5), but partial credit is not recognized in velocity calculations.