PMI-ACP · Question #283

Which following statement is the least accurate regarding the Burndown chart?

The correct answer is C. It provides insight into the quality of the product. A Burndown chart tracks the amount of work remaining (in hours or story points) over time during a Sprint or release. It is updated daily by the Development Team and shows whether the team is on track to complete committed work. It does NOT measure product quality - that is deter

Submitted by paula_co· Apr 18, 2026Adaptive Planning

Question

Which following statement is the least accurate regarding the Burndown chart?

Options

  • AIt is calculated using hours or points
  • BIt is updated by the development team daily
  • CIt provides insight into the quality of the product
  • DIt reflects work remaining

How the community answered

(59 responses)
  • A
    7% (4)
  • B
    2% (1)
  • C
    88% (52)
  • D
    3% (2)

Explanation

A Burndown chart tracks the amount of work remaining (in hours or story points) over time during a Sprint or release. It is updated daily by the Development Team and shows whether the team is on track to complete committed work. It does NOT measure product quality - that is determined through testing, code reviews, defect rates, and quality metrics. Options A, B, and D are all accurate descriptions of a Burndown chart. Conflating velocity/progress tracking with quality is a common misconception this question tests.

Topics

#Burndown chart#Agile metrics#Progress tracking#Sprint management