PMI-ACP · Question #283
Which following statement is the least accurate regarding the Burndown chart?
The correct answer is C. It provides insight into the quality of the product. A Burndown chart tracks the amount of work remaining (in hours or story points) over time during a Sprint or release. It is updated daily by the Development Team and shows whether the team is on track to complete committed work. It does NOT measure product quality - that is deter
Question
Which following statement is the least accurate regarding the Burndown chart?
Options
- AIt is calculated using hours or points
- BIt is updated by the development team daily
- CIt provides insight into the quality of the product
- DIt reflects work remaining
How the community answered
(59 responses)- A7% (4)
- B2% (1)
- C88% (52)
- D3% (2)
Explanation
A Burndown chart tracks the amount of work remaining (in hours or story points) over time during a Sprint or release. It is updated daily by the Development Team and shows whether the team is on track to complete committed work. It does NOT measure product quality - that is determined through testing, code reviews, defect rates, and quality metrics. Options A, B, and D are all accurate descriptions of a Burndown chart. Conflating velocity/progress tracking with quality is a common misconception this question tests.