The best description of a Sprint backlog is:
The correct answer is C. A prioritized list of requirements to be completed during the Sprint. The Sprint Backlog is a subset of the Product Backlog that contains the work items (user stories, tasks) the Development Team has committed to completing within a single Sprint. It is scoped to the current Sprint, not the entire project (eliminating B) or a release (eliminating…
Question
The best description of a Sprint backlog is:
Options
- ADaily progress for a Sprint over the Sprint's length
- BA prioritized list of tasks to be completed during the project
- CA prioritized list of requirements to be completed during the Sprint
- DA prioritized list of requirements to be completed for a release
How the community answered
(22 responses)- A5% (1)
- C95% (21)
Explanation
The Sprint Backlog is a subset of the Product Backlog that contains the work items (user stories, tasks) the Development Team has committed to completing within a single Sprint. It is scoped to the current Sprint, not the entire project (eliminating B) or a release (eliminating D). Option A describes a Burndown chart, which tracks daily progress. The Sprint Backlog is created during Sprint Planning and is owned by the Development Team.