The best description of a Sprint backlog is:

The correct answer is C. A prioritized list of requirements to be completed during the Sprint. The Sprint Backlog is a subset of the Product Backlog that contains the work items (user stories, tasks) the Development Team has committed to completing within a single Sprint. It is scoped to the current Sprint, not the entire project (eliminating B) or a release (eliminating…

Submitted by thandi_sa· Apr 18, 2026Adaptive Planning

Question

The best description of a Sprint backlog is:

Options

  • ADaily progress for a Sprint over the Sprint's length
  • BA prioritized list of tasks to be completed during the project
  • CA prioritized list of requirements to be completed during the Sprint
  • DA prioritized list of requirements to be completed for a release

How the community answered

(22 responses)
  • A
    5% (1)
  • C
    95% (21)

Explanation

The Sprint Backlog is a subset of the Product Backlog that contains the work items (user stories, tasks) the Development Team has committed to completing within a single Sprint. It is scoped to the current Sprint, not the entire project (eliminating B) or a release (eliminating D). Option A describes a Burndown chart, which tracks daily progress. The Sprint Backlog is created during Sprint Planning and is owned by the Development Team.

Topics

#Sprint Backlog#Scrum Artifacts#Agile Planning#Requirements Prioritization