Which of the following sets of tools is least likely to be utilized by an Agile team?
Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #252. The question stem and answer options stay visible for context.
Submitted by chen.hong· Apr 18, 2026Adaptive Planning
Question
Which of the following sets of tools is least likely to be utilized by an Agile team?
Options
- ADigital camera, task board
- BWiki, planning poker cards
- CWBS, PERT charts
- DSmart board, card wall
Unlock PMI-ACP to see the answer
You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile tools#Traditional planning#WBS#PERT charts