PMI-ACP · Question #252
PMI-ACP Question #252: Real Exam Question with Answer & Explanation
The correct answer is C: WBS, PERT charts. A Work Breakdown Structure (WBS) and PERT (Program Evaluation and Review Technique) charts are traditional, plan-driven (waterfall) project management tools that rely on detailed upfront planning and fixed scope. Agile teams favor lightweight, adaptive tools such as task boards,
Question
Which of the following sets of tools is least likely to be utilized by an Agile team?
Options
- ADigital camera, task board
- BWiki, planning poker cards
- CWBS, PERT charts
- DSmart board, card wall
Explanation
A Work Breakdown Structure (WBS) and PERT (Program Evaluation and Review Technique) charts are traditional, plan-driven (waterfall) project management tools that rely on detailed upfront planning and fixed scope. Agile teams favor lightweight, adaptive tools such as task boards, card walls, wikis, planning poker cards, and smart boards that support iterative development and collaboration. The other answer choices all contain tools commonly associated with Agile practices.
Topics
Community Discussion
No community discussion yet for this question.