PMI-ACP · Question #239
Project X has an IRR of 12%, and Project Y has an IRR of 10%. Which project should be chosen as a better investment for the organization?
The correct answer is C. Project X. Internal Rate of Return (IRR) measures the profitability of an investment. All else being equal, a higher IRR indicates a better return, so Project X (12%) is the better investment over Project Y (10%). While payback period and NPV are also useful metrics, the question asks to…
Question
Project X has an IRR of 12%, and Project Y has an IRR of 10%. Which project should be chosen as a better investment for the organization?
Options
- AIt depends on the payback period
- BProject Y
- CProject X
- DProject or Y, depending on the NPV
How the community answered
(61 responses)- A3% (2)
- B5% (3)
- C84% (51)
- D8% (5)
Explanation
Internal Rate of Return (IRR) measures the profitability of an investment. All else being equal, a higher IRR indicates a better return, so Project X (12%) is the better investment over Project Y (10%). While payback period and NPV are also useful metrics, the question asks to compare based on IRR alone.
Topics
Community Discussion
No community discussion yet for this question.