nerdexam
PMI

PMI-ACP · Question #23

Which of the following items is not a benefit associated with product demonstrations?

The correct answer is C. Learn about feature estimates. Product demonstrations (e.g., sprint reviews) allow stakeholders to see working software and provide feedback. This feedback can reveal whether a feature is suitable for the intended purpose (suitability), whether it is easy to use (usability), and whether there are additional…

Submitted by devops_kid· Apr 18, 2026Value-driven Delivery

Question

Which of the following items is not a benefit associated with product demonstrations?

Options

  • ALearn about feature suitability
  • BLearn about feature usability
  • CLearn about feature estimates
  • DLearn about new requirements

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    92% (33)

Explanation

Product demonstrations (e.g., sprint reviews) allow stakeholders to see working software and provide feedback. This feedback can reveal whether a feature is suitable for the intended purpose (suitability), whether it is easy to use (usability), and whether there are additional requirements that need to be added. However, demonstrations are not used to learn about estimates - estimation is done during planning ceremonies such as backlog refinement or sprint planning, not during demos.

Topics

#Product Demonstrations#Agile Feedback#Stakeholder Engagement

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice